Commercial Cooking System Plan Review Requirements
1. Provide two (2) sets of plans and
specifications signed and sealed by a
registered design
professional licensed in the state where the construction
is
to be performed. The following information, when applicable, is to
be
provided:
Hood
System
·
Canopy or non-canopy.
·
Material, gauge, joints welded, surface
·
Exhaust CFM.
·
Make-up air.
·
Grease removal device, size, accessibility and angle.
·
Clearances.
Duct Construction and
Termination
·
Each independent system.
·
Material, gauge and connection to hood.
·
Collection points.
·
Air velocity.
·
Cleanout location.
·
Penetration protection.
·
Clearances.
·
Front lot line, air intake, above roof
·
Above adjoining ground level.
·
Weather protection, penetration protection.
·
Clearances.